You add task information, but the schedule doesn’t change.
-- part contents for background part 7
----- text -----
Display all dates around task boxes in the Schedule Chart, or uncover their columns in the Project Table. Trace the path through the dates to see if it makes sense.
Check the start and finish time of each task by displaying hours and minutes along with dates as attributes in the Schedule Chart. A 1-day task starts and ends on the same date, which may be confusing if the dates are displayed without the time of day.
-- part contents for card part 22
----- text -----
1 of 6
-- part contents for background part 6
----- text -----
Verify that AutoCalc is on. This command has a check mark beside it in the Dates menu when it is on.
To be sure that all subproject information has been integrated into the master project, use Consolidate Project Family from the Dates menu.